Becker, Sherburne County, MN
Amazon Becker Data Center
Also known as AWS Becker, Amazon Data Services Becker
- Rumored
- Proposed
- Approved
- Under construction
- Operating
- Paused
Amazon Data Services bought a roughly 348-acre site next to Xcel Energy's Sherco coal plant in Becker, closing on October 30, 2024, for a planned data center. In February 2025, state regulators ruled that its plan for about 250 diesel backup generators needed a Certificate of Need; the data center’s expected peak daily load was 600 MW. Amazon suspended the project in May 2025 while state lawmakers debated data center tax breaks, and said it would keep the property.
Key facts
Size & schedule
| Planned capacity | 600 MW [2] expected peak daily load |
|---|---|
| Site size | 348 acres [1] site purchased for $73.56 million |
| Permanent jobs (promised) | 100 [1] |
| Construction jobs | 1,200 [1] building trade jobs |
Power
| Utility | Xcel Energy [1] statement by Xcel spokesman Kevin Coss Source excerpt“As the electric provider for the area, we will be engaged in the site development process and providing the electricity needed to reliably power the site once operational.” |
|---|---|
| Power supply | About 250 Tier 4 diesel backup generators (250 kW to 2.75 MW each) proposed [2] |
| Utility commission case | Minnesota PUC Docket No. PT7151/CN-24-435 [5] Certificate of Need proceeding for backup generators Source excerpt“Docket No. PT7151/CN-24-435” |
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
Elk River Technologies buys the site from Xcel Energy for $7.97 million [1]
Amazon Data Services closes on the 348-acre site for $73.56 million [1]
Amazon asks the Minnesota PUC to exempt its backup generators from Certificate of Need requirements (Docket PT7151/CN-24-435) [5]
Minnesota PUC rules the backup generators require a Certificate of Need [2]
Amazon says it is suspending its development activities in Minnesota but will keep the property [3]
Issues raised
- Opponents objected to the environmental review of about 250 diesel backup generators; CURE argued the 600 MW plan was twelve times the Certificate of Need threshold [5]
- City officials said the pause was a blow: the project would have nearly replaced about $5 million a year in Sherco tax revenue, roughly 40% of the school district's local tax income [4]
- Amazon cited 'uncertainty' as state lawmakers debated repealing a sales tax break on data center electricity [3]
Sources
- Amazon Data Services buys site slated for data center near Sherco in BeckerMinnesota Star Tribune · Nov 13, 2024 · news
- Minnesota Regulators Rule That Certificate of Need is Required for Backup Generators at Data CenterAmerican Public Power Association · Mar 8, 2025 · news
- Amazon pulls back on plans for large data center in BeckerMPR News · May 23, 2025 · news
- Amazon's retreat from its planned Minnesota data center is latest 'gut punch' for BeckerMinnesota Star Tribune · Sep 9, 2025 · news
- Initial Comments of CURE regarding Amazon Data Services, Inc.'s Petition for Exemption from Certificate of Need RequirementsCURE · Jan 31, 2025 · other
- Amazon Web Services suspends plans for Minnesota data centerDatacenterDynamics · May 28, 2025 · news