Mount Pleasant, Racine County, WI

Microsoft Fairwater

Also known as Microsoft Mount Pleasant datacenter

OperatingFirst facility complete June 2026; second facility under construction, target 2028; up to 15 more data centers approved Jan 2026
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

Microsoft's Fairwater AI datacenter sits on a 315-acre site in the Village of Mount Pleasant. Microsoft calls it the world's most powerful AI datacenter. The company announced in June 2026 that construction of the first facility was complete, with equipment online since April 2026. A second facility of similar scale is under construction for 2028, and in January 2026 the Village Board approved up to 15 more Microsoft data centers northwest of the site. Three nearby Sturtevant residents sued Microsoft over noise in July 2026.

Key facts

Size & schedule

Site size315 acres [4]
existing site
Floor area9 million sq ft [2]
nearly 9 million sq ft planned for the 15 additional data centers approved Jan 2026, with 3 new substations
Stated investment$7 billion [1]
company says 'more than $7 billion': $3.3B initial plus $4B more for a second datacenter
Permanent jobs (promised)800 [3]
about 550 full-time at first facility; about 800 once second facility operates (company figures)
Construction jobs3,000 workers [1]
3,000+ at peak construction, per Microsoft
Target completionSecond facility 2028 [3]

Power

UtilityWe Energies [6]
15-year electric service contract signed July 16, 2026
Source excerpt
“Microsoft's new 15-year electric service contract for its Mount Pleasant data center includes a provision Wisconsin regulators previously rejected.”
Power supplyMicrosoft says it will match fossil-fuel power with carbon-free energy; 250 MW solar project in Portage County under construction [1]
Backup generators40 emergency generators and two emergency fire pumps at the 1.3 million sq ft facility; 39 backup generators at the existing facility [8]
ultra-low sulfur diesel and/or hydrotreated vegetable oil; per WDNR as reported by WPR
Source excerpt
“The new 1.3 million-square-foot data center will include 40 emergency electric generators with pollution controls and two emergency fire pumps, according to the Wisconsin Department of Natural Resources.”
Air permitWDNR construction permit application 24-MIN-238 and operation permit revision 25230249A-F03 (six new and two revised data centers); public hearing Dec. 2, 2024 [7]
Source excerpt
“The public hearing will be held on Dec. 2, 2024, at 2:00 pm.”

Water

Water sourceRacine water; the expansion's annual requirement is not to exceed 8.4 million gallons [2]
Coolingclosed-loop liquid cooling for over 90% of facility; outside air for the rest, with water only on the hottest days [1]

Money & incentives

Tax incentivesLocated in Village of Mount Pleasant Tax Incremental District No. 5, created in 2017 for Foxconn [9]
Source excerpt
“TID No. 5 was created in November 2017 for the Foxconn project and includes about 3,900 acres of Business Park-zoned land along the Interstate 94 corridor”

Local decisions & site

ZoningBusiness Park-zoned land within TID No. 5 [9]
Source excerpt
“TID No. 5 was created in November 2017 for the Foxconn project and includes about 3,900 acres of Business Park-zoned land along the Interstate 94 corridor”
Parcel / address4800 90th Street, Mount Pleasant, Racine County (FID 252302490) [7]
Source excerpt
“Microsoft Mount Pleasant Data Centers, located at 4800 90th Street, Mount Pleasant, Racine County, Wisconsin, FID 252302490”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Lawsuits

Sturtevant residents v. Microsoft (noise class action)pending [5]
Three Sturtevant residents filed a class action alleging private nuisance and negligence from data center noise.
U.S. District Court for the Eastern District of Wisconsin · filed Jul 1, 2026
Source excerpt
“The class action lawsuit was filed Wednesday in the U.S. District Court for the Eastern District of Wisconsin by three residents of Sturtevant who live near the data center.”

Timeline

  1. Village of Mount Pleasant approves purchase and sale, development and implementation agreements with Microsoft for about 315 acres in TID 5 [10]

  2. Microsoft announces Mount Pleasant datacenter [3]

  3. Microsoft details Fairwater and commits $4B to a second datacenter [1]

  4. Mount Pleasant Village Board unanimously approves up to 15 additional Microsoft data centers [2]

  5. Equipment brought online at first facility [3]

  6. Microsoft announces construction of first facility is complete [3]

  7. Three Sturtevant residents sue Microsoft in federal court over noise [5]

  8. Microsoft signs 15-year electric service contract with We Energies [6]

Issues raised

  • Three Sturtevant residents allege excessive noise from diesel generators and HVAC, including low-frequency infrasound, in a federal suit [5]
  • Three residents raised concerns at the January 2026 expansion approval; six spoke in favor [2]

Sources

  1. Made in Wisconsin: The world's most powerful AI datacenter
    Microsoft On the Issues · Sep 18, 2025 · company
  2. Microsoft gains approval for 15 new data centers in Wisconsin
    w.media · Jan 27, 2026 · news
  3. Microsoft completes construction on first datacenter facility in Mount Pleasant, Wisconsin
    Microsoft Source · Jun 23, 2026 · company
  4. Microsoft finishes construction of Mount Pleasant data center, plans for more
    WPR · Jun 23, 2026 · news
  5. Microsoft sued over noise complaints at new Mount Pleasant data center facility
    WPR · Jul 2, 2026 · news
  6. Microsoft-We Energies contract retains provision PSC struck down
    Wisconsin Watch · Aug 6, 2026 · news
  7. Microsoft Corporation Data Center Construction (24-MIN-238) And Operation Permit (25230249A-F03) Public Hearing
    Wisconsin Department of Natural Resources · Dec 2, 2024 · government
  8. Microsoft to use diesel-fired generators as backup power for data centers
    WPR · Nov 15, 2024 · news
  9. Mt. Pleasant creates project review committee for TID housing Microsoft data centers
    JT Irregulars · Aug 2026 · news
  10. Village of Mount Pleasant Approves Agreements with Microsoft
    Village of Mount Pleasant (via Urban Milwaukee) · Mar 30, 2023 · government