Harlem, Columbia County, GA
Pumpkin Technology Campus
Also known as Pumpkin Center Data Center, Pumpkin Center
- Rumored
- Proposed
- Approved
- Under construction
- Operating
The Pumpkin Technology Campus is a data center campus proposed by Houston firm Cloverleaf Infrastructure, as Piedmont DevCo LLC, and the Prather Company on approximately 420 acres along I-20 and Appling Harlem Road in Harlem, Columbia County. Concept plans depict four data center buildings, two warehouses, an office and a substation. The Columbia County Board of Commissioners approved the rezoning 4-1 in February 2026; a resident's judicial review petition was dismissed with prejudice in March 2026, and he filed a notice of appeal in April.
Key facts
Size & schedule
| Site size | 420 acres [1] approximately; four parcels Source excerpt“DevCo applied to rezone a group of four parcels along I-20 and Appling Harlem Road owned by the Prather family, totaling approximately 420 acres” |
|---|---|
| Buildings | 4 [1] four data center buildings, each more than 717,000 sq ft, plus two 180,000 sq ft warehouses, an office and a substation (concept plans) Source excerpt“Concept plans for the Pumpkin Technology Campus depict four data center buildings, each more than 717,000 square feet, two 180,000-square foot warehouses, an office, a substation, several stormwater ponds and a buffer around the perimeter.” |
| Stated investment | $1 billion [1] value stated in rezoning application materials Source excerpt“from Planned Unit Development (PUD) to the new Data Center (D-C) district zoning for the development of the new facility, a project that the accompanying states is worth $1 billion.” |
| Permanent jobs (promised) | 200-300 [8] developer-stated range Source excerpt“The developer says the data center would employ 200-300 workers.” |
| Construction jobs | 1,500 [1] approximately Source excerpt“will provide some 1,500 construction jobs, and employ between 200 to 300 people once in operation.” |
Local decisions & site
| Deciding vote | Columbia County Board of Commissioners approved the rezoning 4-1 in February 2026, Commissioner Allison Couch opposed; conditions raised buffers from 250 to 500 feet and berms from 6 to 12 feet [4]Source excerpt“The Pumpkin Center project faced the most public opposition but was approved 4-1, with Commissioner Allison Couch voting against it.” |
|---|---|
| Zoning | Rezoned from Planned Unit Development (PUD) to Data Center (D-C) district [1]Source excerpt“totaling approximately 420 acres, from Planned Unit Development (PUD) to the new Data Center (D-C) district zoning for the development of the new facility” |
| Parcel / address | Four parcels along I-20 and Appling Harlem Road owned by the Prather family [1]Source excerpt“DevCo applied to rezone a group of four parcels along I-20 and Appling Harlem Road owned by the Prather family” |
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Lawsuits
| Gregory P. Guido Jr. petition for judicial review (Pumpkin Center rezoning) | appealed [7] Petition alleging procedural defects, incomplete analysis and conflicts with the county's comprehensive plan was dismissed with prejudice on March 25, 2026, and the petitioner filed a notice of appeal in April 2026. Columbia County Superior Court; appeal to Georgia Court of Appeals · filed Feb 25, 2026 Source excerpt“Those petitions alleged issues including procedural defects, incomplete analysis and conflicts with the county's comprehensive plan.” |
|---|
Timeline
Piedmont DevCo LLC applies to rezone about 420 acres for the Pumpkin Technology Campus [1]
Columbia County Planning Commission votes 4-1 to recommend the Pumpkin Center and Byrd Farm data center projects [3]
Board of Commissioners approves the rezoning 4-1 with larger buffers and berms [4]
Resident Gregory P. Guido Jr. files a judicial review petition challenging the Pumpkin Center rezoning [6]
Superior Court order dismissing the Pumpkin Center petition with prejudice is signed and filed [7]
Guido files notices of appeal of the dismissals [7]
Issues raised
- Residents raised health concerns about diesel generator emissions, noise and water use [5]
- Greenpoint neighborhood residents say they bought homes expecting nearby shopping and restaurants under earlier development plans [3]
- A resident's petition alleged the rezoning was approved despite an incomplete Development of Regional Impact review [6]
Sources
- Data center project proposed along Appling Harlem RoadThe Augusta Press · Dec 15, 2025 · news
- Three proposals for data centers in Columbia County, Georgia, meet stiff oppositionDatacenterDynamics · Jan 9, 2026 · news
- Columbia County data centers recommended for approval despite residents' concernsWRDW · Jan 14, 2026 · news
- Columbia County approves 2 data centers, rejects 1WRDW · Feb 3, 2026 · news
- Columbia County passes two out of three rezonings for data center requests amid persistent oppositionThe Augusta Press · Feb 5, 2026 · news
- Citizen files lawsuits over Columbia County data centersWRDW · Feb 25, 2026 · news
- Citizen appeals dismissals of Columbia County data center rezoning lawsuitsWRDW · Apr 16, 2026 · news
- 2 more data centers now being proposed in Columbia CountyWALB · Dec 17, 2025 · news