Grayslake, Lake County, IL
T5 @ Chicago IV
- Rumored
- Proposed
- Approved
- Under construction
- Operating
The T5 @ Chicago IV campus in Grayslake, as approved by the Village Board between September 2024 and May 2025, calls for up to 472 acres of development, more than 10 million square feet of buildings and an electrical demand of approximately 1.55 gigawatts supplied by ComEd. Village officials describe an expected $18 billion multi-building private investment, and the village issued the first building permit, for an 800,000-square-foot facility, on Sept. 1, 2026. A lawsuit filed in Lake County Circuit Court by the Preservation of Community Well-being Collective LLC and nine Lake County residents challenges the village's approvals.
Key facts
Size & schedule
| Planned capacity | 1.55 GW [4] approximate electrical demand supplied by ComEd Source excerpt“calls for up to 472 acres of development, more than 10 million square feet of buildings and an electrical demand of approximately 1.55 gigawatts of power supplied by ComEd” |
|---|---|
| Planned capacity | 480 MW [1] critical IT capacity for a 160-acre site as announced by T5 in May 2024, before the approved expansion to 472 acres Source excerpt“The 160-acre site will support up to 480 megawatts (MW) of critical IT capacity across multiple data center buildings.” |
| Site size | 472 acres [4] up to Source excerpt“calls for up to 472 acres of development, more than 10 million square feet of buildings and an electrical demand of approximately 1.55 gigawatts of power supplied by ComEd” |
| Floor area | 10.1 million sq ft [3] as much as Source excerpt“In Grayslake, the T5 project calls for as many as 18 buildings totaling as much as 10.1 million square feet.” |
| Buildings | 18 [3] as many as Source excerpt“In Grayslake, the T5 project calls for as many as 18 buildings totaling as much as 10.1 million square feet.” |
| Stated investment | $18 billion [4] expected, per village officials Source excerpt“The first facility, spanning 800,000 square feet, marks the operational start of an expected $18 billion multi-building private investment, village officials said.” |
| Target completion | First 60MW in Q4 2027 (as announced May 2024) [1]Source excerpt“the first 60MW of data center capacity in Q4 2027” |
Power
| Utility | ComEd [4]Source excerpt“an electrical demand of approximately 1.55 gigawatts of power supplied by ComEd, with associated diesel backup generation infrastructure.” |
|---|---|
| Backup generators | diesel backup generation infrastructure [4]Source excerpt“an electrical demand of approximately 1.55 gigawatts of power supplied by ComEd, with associated diesel backup generation infrastructure.” |
Money & incentives
| Tax incentives | None: secured without local municipal tax incentives, tax exemptions or TIF subsidies (per village); projected $1.4 billion in property tax revenue over 20 years [3]Source excerpt“Secured without local municipal tax incentives, tax exemptions or TIF (tax increment financing) subsidies, the development is projected to generate $1.4 billion in property tax revenue over 20 years across local taxing bodies” |
|---|
Local decisions & site
| Deciding vote | Approved by the Grayslake Village Board between September 2024 and May 2025 [4]Source excerpt“The T5 @ Chicago IV campus, as approved by the Grayslake Village Board between September 2024 and May 2025” |
|---|---|
| Parcel / address | Cornerstone property along Peterson Road and Alleghany Road [4]Source excerpt“The Village of Grayslake said Tuesday that it issued the initial building permit for the first facility at the T5 campus within the Cornerstone property along Peterson Road and Alleghany Road.” |
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Upcoming hearings
- Oct 30, 2026 — Lake County Circuit Court: Initial status hearing in lawsuit challenging the village's approvals (9 a.m., Courtroom 301) [4]
Timeline
T5 announces a 480 MW data center campus in Grayslake [1]
Grayslake Village Board completes approvals of the campus (approved between September 2024 and May 2025) [4]
Preservation of Community Well-being Collective LLC and nine Lake County residents sue to challenge the village's approvals [4]
Village issues first building permit, for an 800,000-square-foot facility [4]
Issues raised
Sources
- T5 Data Centers Announces Further Expansion into Chicago Suburbs with New 480 MW Data Center CampusT5 Data Centers · May 2, 2024 · company
- Despite village approvals, legal action expected against Grayslake data centerDaily Herald · Jun 8, 2026 · news
- Defying trends, Grayslake welcomes start of massive data center projectDaily Herald · Sep 1, 2026 · news
- Grayslake issues first permit for construction to begin on mega data center campus as lawsuit seeks to block developmentLake and McHenry County Scanner · Sep 1, 2026 · news