Amazon Data Services King George campus (former Birchwood power plant site)

King George County, VADeveloper: Amazon (AWS)

Also known as Birchwood data center campus

PausedCounty board withdrew from the performance agreement in January 2024; Amazon's vested-rights lawsuit against the county was set for trial September 28-29, 2026
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating
Paused

Amazon Data Services planned to invest up to $6 billion in 17 data centers on 869 acres at and around the former Birchwood Power Facility in the Sealston area of King George County, under a performance agreement approved in December 2023. A new board majority reversed the county commitment on January 2, 2024, and after the Board of Zoning Appeals denied Amazon's vested-rights request in March 2025, Amazon took the dispute to King George County Circuit Court. Trial dates of September 28 and 29 were set in 2026.

Site size
869 acres
Permanent jobs (promised)
100
projected, not guaranteed

Key facts

Size & schedule

Site size869 acres [2]
Source excerpt
“to deny the company's request for a determination of vested rights of 869 acres it owns in the county for the purpose of constructing a data center campus”
Site size893 acres [4]
figure reported by a different outlet; conflicts with 869 acres
Source excerpt
“the 893-acre former Birchwood Power Plant”
Floor area7 million sq ft [4]
Source excerpt
“a 7-million square foot data center campus”
Buildings17 [3]
full buildout, as described by Amazon
Source excerpt
“In King George, Amazon says it planned to invest up to $6 billion in 17 data centers in the full buildout of 869 acres at the site of the former Birchwood Power Facility.”
Stated investment$6 billion [1]
capital investment by June 30, 2040 under the proposed performance agreement
Source excerpt
“Amazon Data Services intends to invest $6 billion in capital investment in King George County by June 30, 2040”
Permanent jobs (promised)100 [1]
projected, not guaranteed
Source excerpt
“Amazon projects but does not guarantee at least one hundred permanent, full-time jobs in the County”

Water

Water sourceAgreement contemplated Amazon providing at least 600,000 gallons per day of raw surface water to the county at no charge [2]
Source excerpt
“through which the company would provide at least 600,000 gallons of raw surface water per day to the county at no charge”

Money & incentives

Tax incentivesCounty to maintain existing tax rate and depreciation schedule for computer equipment; infrastructure grant based on estimated minimum $336,360,000 infrastructure spend [1]
Source excerpt
“The County will maintain the existing tax rate and depreciation schedule for personal property classified as Computer Equipment”

Local decisions & site

Parcel / addressFormer Birchwood power plant site and surrounding properties in the Sealston area [1]
Source excerpt
“develop data center campuses at the former Birchwood power plant site and other surrounding properties in the Sealston area”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Lawsuits

Amazon's vested-rights appeal against King George Countypending [3]
Amazon appealed the Board of Zoning Appeals' decision upholding the zoning administrator's refusal to certify its vested rights, seeking to confirm those rights and prevent a downzoning; trial was rescheduled to September 2026.
King George County Circuit Court · filed May 2025
Source excerpt
“The company filed a lawsuit in circuit court last May to appeal the zoning board decision”

Upcoming hearings

  • Sep 28, 2026 — King George County Circuit Court: Trial dates of September 28 and 29 set in Amazon Data Services v. King George County Board of Supervisors [4]

Timeline

  1. County staff report on proposed $6 billion performance agreement with Amazon Data Services presented to Board of Supervisors [1]

  2. Board approves the performance agreement; Amazon buys the property for almost $169 million [3]

  3. New board majority reverses the county's commitment [3]

  4. Supervisors unanimously ask the Planning Commission to reconsider the rezoning of more than 500 acres [5]

  5. Board of Zoning Appeals denies Amazon's request for a vested-rights determination [2]

  6. Amazon files an 878-page petition in King George County Circuit Court [2]

Issues raised

  • The project remains the subject of a pending lawsuit against the county [6]
  • Residents raised concerns about wildlife, noise, water usage and electricity from data centers in the county [6]

Sources

  1. Board of Supervisors Agenda Item: Proposed Performance Agreement with Amazon Data Services for Local Economic Development Incentives
    King George County · Nov 14, 2023 · government
  2. Amazon taking fight with King George supervisors to court
    Fredericksburg Free Press · May 6, 2025 · news
  3. Virginia Court Case Could Influence Other Data Center Fights
    GovTech (Richmond Times-Dispatch) · May 4, 2026 · news
  4. Motions Filed This Week in Amazon Data Services v. King George County
    Fredericksburg Advance · May 6, 2026 · news
  5. Prime real estate? King George supervisors request reversal of rezoned Amazon properties
    Fredericksburg Free Press · Apr 3, 2024 · news
  6. 'This should've happened last year:' King George residents protest already-approved data centers
    Fredericksburg Free Press · Jun 3, 2026 · news