Cheyenne, Laramie County, WY
Meta Cheyenne Data Center
Also known as Project Cosmo, Goat Systems LLC
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Meta is building an $800 million data center, known during development as Project Cosmo, on a 960-acre parcel in the High Plains Business Park in south Cheyenne. It is expected to go online in 2027. In 2026 the Cheyenne Board of Public Utilities traced a bacterial contamination of the city's reuse water system to the project's fill-and-flush operations and stopped accepting that wastewater from data centers.
Key facts
Size & schedule
| Site size | 960 acres [2]Source excerpt“a 960-acre parcel of land in the High Plains Business Park” |
|---|---|
| Floor area | 715,000 sq ft [1] other outlets report 750,000 and roughly 800,000 sq ft Source excerpt“715,000 sq ft (66,425 sqm) campus” |
| Stated investment | $800 million [1] more than $800 million (company-stated) Source excerpt“invest more than $800 million” |
| Permanent jobs (promised) | 100 [3]Source excerpt“will employ 100 operations positions when completed” |
| Construction jobs | 1,000 [3] over 1,000 skilled trades people, temporarily Source excerpt“will temporarily employ over 1,000 skilled trades people” |
| Target completion | 2027 [2]Source excerpt“expected to go online in 2027” |
Power
| Utility | Cheyenne Light, Fuel & Power (Black Hills Energy) [6]Source excerpt“Cheyenne, Wyoming, an area served by the company's electric utility, Cheyenne Light, Fuel & Power Company” |
|---|---|
| Power supply | Black Hills Energy grid, with new resources including renewables (company-stated) [1]Source excerpt“work with Black Hills Energy to add new resources to the grid, including renewables” |
Water
| Cooling | First phase closed-loop; second phase evaporative [4]Source excerpt“The first phase under construction uses a closed-loop cooling system, while the second phase will use evaporative cooling.” |
|---|---|
| Water permit | Cheyenne BOPU revoked Goat Systems LLC's industrial discharge privileges for fill-and-flush operations effective March 24, 2026 [5]Source excerpt“revoked the company's industrial discharge privileges for those operations effective March 24” |
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
Cowboy State Daily reports Meta is behind the Project Cosmo data center in south Cheyenne [7]
Meta unveils the $800 million Project Cosmo data center [2]
BOPU revokes the company's industrial discharge privileges for fill-and-flush operations [5]
BOPU announces it will no longer accept industrial wastewater from data center fill-and-flush or closed-loop cooling operations [4]
Issues raised
- The city found Goat Systems LLC in 'significant noncompliance' with industrial pretreatment rules after Cupriavidus gilardii bacteria contaminated the municipal reuse water system [5]
- Meta says its contractor Fortis immediately stopped discharging industrial wastewater and began hauling it offsite [4]
Sources
- Meta officially announces data center in Cheyenne, WyomingDatacenterDynamics · Jul 3, 2024 · news
- $800 million Project Cosmo unveiled as Meta data centerWyoming Tribune Eagle · Jul 2, 2024 · news
- Meta announces $800 million data center in CheyenneWyoming Public Media · Jul 8, 2024 · news
- Cheyenne BOPU traces rare bacteria discharge to Meta data center contractorWyoming Tribune Eagle · Jul 2, 2026 · news
- Cheyenne Won't Take Data Center Wastewater After Meta Contractor Contaminated SystemCowboy State Daily · Jul 2, 2026 · news
- Black Hills Corp. to Power Meta's New Data Center in Wyoming with Innovative Energy Solutions and Mission-Critical ReliabilityBlack Hills Corp. · Jul 11, 2024 · utility
- EXCLUSIVE: Meta Coming To Cheyenne; Multibillion-Dollar Data Center PlannedCowboy State Daily · May 9, 2024 · news