Cheyenne, Laramie County, WY

Project Tembo

Also known as Project Jade, Crusoe/Tallgrass Cheyenne AI data center

ApprovedCounty approved the original site plans Jan. 2026. Crusoe left in spring 2026, and Google (Jupiter Star Holdings) resubmitted a smaller site plan in July 2026. Tallgrass's power hub is under construction.
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

Project Tembo, first announced as Crusoe and Tallgrass's Project Jade, is a planned AI data center campus in the Switchgrass Industrial Park, 8 miles south of Cheyenne, powered by Tallgrass's 2.7 GW natural gas power hub. Laramie County commissioners unanimously approved the Crusoe site plans on January 6, 2026. Crusoe paused its work and left in spring 2026. A June 30, 2026 county filing identified Google, through Jupiter Star Holdings, as the owner of a scaled-down 716-acre, four-building plan with completion targeted for 2031.

Key facts

Size & schedule

Planned capacity2.7 GW [3]
Tallgrass power hub capacity; scalable to 10 GW; originally announced at 1.8 GW
Site size716 acres [4]
Floor area3.1 million sq ft [5]
reduced from 4,025,500 sq ft
Buildings4 [5]
reduced from five in the Crusoe plan
Stated investment$17 billion [7]
per Wyoming Public Media; Tallgrass separately investing $7 billion in power plants [6]; other reports cite $50 billion
Permanent jobs (promised)250 [7]
Construction jobs2,500 [5]
peak; reduced from 5,000
Target completion2031 [4]

Power

Power supplyTallgrass BFC Power / Cheyenne Power Hub natural gas plants plus Black Hills Energy resources and fuel cells [4]
On-site generation typeTwo combined cycle power plants plus temporary and permanent aeroderivative turbines and a fuel cell yard (BFC Power and Cheyenne Power Hub) [10]
Source excerpt
“The power generation component, designated as the BFC Power and Cheyenne Power Hub Project, would include two combined cycle power plants, along with temporary and permanent aeroderivative turbines intended to provide startup, backup, and base load supplemental generation, according to site plan documents.”

Water

Water sourcedeep wells beneath the local aquifer [7]
Coolingclosed-loop, air-cooled [7]

Local decisions & site

ZoningZone change to Switchgrass Industrial Park Planned Unit Development (PUD); Google's reduced site plan revision (PZ-26-00058) processed administratively; separate Class B conditional use permit (PZ-26-00057) for an office complex [5]
Source excerpt
“It received governing body approvals for a Zone Change to Switchgrass Industrial Park Planned Unit Development (PUD) as well as the Commercial Site Plan, and all of these approvals included a robust public comment period as well as public hearings.”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Timeline

  1. Crusoe and Tallgrass announce a 1.8 GW AI data center in southeast Wyoming [1]

  2. Laramie County commissioners unanimously approve the Project Jade site plans [2]

  3. Crusoe pauses development 'at the request of our customer' and leaves the project [6]

  4. Site-plan amendment filing with the county identifies Google as the owner [4]

  5. County memo on the site plan resubmittal and conditional use permit for Project Tembo [5]

  6. County Planning Commission holds a hearing on the office complex conditional use permit [5]

  7. Google holds a community open house in Cheyenne [9]

Issues raised

  • Residents raised concerns about water depletion, aquifer and PFAS contamination, wildlife migration, noise, light and traffic [2]
  • Google pledged to replenish 120% of the freshwater it consumes across its operations by 2030 [7]

Sources

  1. Crusoe and Tallgrass Announce AI Data Center in Wyoming
    Tallgrass · Jul 24, 2025 · company
  2. Laramie County approves construction of what could become the largest data center in US
    WyoFile · Jan 20, 2026 · news
  3. Huge Cheyenne Data Center Grows To 2.7 Gigawatts — Nearly Triple State Power Use
    Cowboy State Daily · Jan 8, 2026 · news
  4. Say Hello To Google, The Mystery Owner Behind Wyoming's Largest Data Center Project
    Cowboy State Daily · Jul 8, 2026 · news
  5. Commercial Site Plan Re-Submittal and Conditional Use Permit for Project Tembo Data Center
    Laramie County · Jul 8, 2026 · government
  6. Crusoe pulls out of Project Jade data center
    Wyoming Tribune Eagle · Jun 9, 2026 · news
  7. Google promises to replenish local watershed at open house in Cheyenne
    Wyoming Public Media · Sep 17, 2026 · news
  8. Google is customer behind 2.7GW data center campus near Cheyenne, Wyoming
    DatacenterDynamics · Jul 14, 2026 · news
  9. Google outlines $17B Project Tembo data center campus in Laramie County
    Gillette News Record · Sep 11, 2026 · news
  10. Wyoming data center power projects highlight new entrants, partnerships in power generation market
    Power Engineering · May 28, 2026 · news