Falls Township, Bucks County, PA
Falls Township Innovation Campus
Also known as Amazon Keystone Trade Center data center
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Amazon is building a data center campus on about 250 acres within the Keystone Trade Center in Falls Township. Amazon plans 2 million square feet of data center space across 10 buildings. It has approval for 72 diesel emergency engines and has applied for 280 natural gas-fired backup generator engines. Nearly 5,000 people have signed a petition calling for a moratorium on data centers in the township.
Key facts
Size & schedule
| Site size | 250 acres [1] approximately Source excerpt“approximately 250 acres within the Keystone Trade Center” |
|---|---|
| Floor area | 2 million sq ft [2]Source excerpt“Amazon plans 2 million square feet of data center space across 10 buildings for cloud computing and AI.” |
| Buildings | 10 [2]Source excerpt“Amazon plans 2 million square feet of data center space across 10 buildings for cloud computing and AI.” |
| Stated investment | $20 billion [1]Source excerpt“at least $20 billion” |
Power
| Backup generators | 72 diesel-fired emergency engines approved; 280 natural gas-fired backup generator engines (4,287 hp each) applied for [2]Source excerpt“Amazon has also applied to install 280 natural gas-fired 'critical backup generator engines' at 4,287 horsepower each.” |
|---|---|
| Air permit | Five air and water discharge permits approved, including 72 diesel-fired emergency engines; separate application for 280 gas-fired engines drew 1,236 comments to DEP [2]Source excerpt“Amazon has been approved for five environmental air and water discharge permits. That includes approval last year for 72 diesel-fired emergency engines.” |
Water
| Cooling | Water-based cooling less than 2% of the year [1]Source excerpt“only use water-based cooling for less than 2% of the year” |
|---|
Local decisions & site
| Deciding vote | Falls Township approved the project in March 2025 [2]Source excerpt“The amendment would have no impact on Amazon’s data center, which the township approved in March 2025.” |
|---|
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
Construction starts (summer 2025, per Amazon) [1]
Falls Township approves the project [2]
Amazon announces its intent to build a data center in Falls Township as part of a $20 billion Pennsylvania investment [3]
Governor's executive order removes data centers, including Amazon's, from the state fast-track permitting program [2]
Issues raised
Sources
- Falls Township Innovation Campus - Amazon Innovation Campuses in PennsylvaniaAmazon · Sep 8, 2026 · company
- Could a Bucks County Amazon data center be affected by Gov. Shapiro's order?The Philadelphia Inquirer · Aug 20, 2026 · news
- Amazon to Open Data Center at NorthPoint Development in FallsFalls Township · Jun 9, 2025 · government
- Falls Township Rewrites Zoning Rules After Amazon Data Center BacklashBucksCo.Today · Aug 7, 2026 · news
- With Data Center Being Built In Falls Twp., Governor Calls For Standards Amid GrowthLevittownNow.com · Feb 4, 2026 · news